GOMACO World Index --- GOMACO World 43.1 - September 2015

Runway Success on a Southern Florida International Airport

 

Fort Lauderdale-Hollywood International Airport

The Fort Lauderdale-Hollywood International Airport in Broward County, Florida, was dealing with departure delays on every single flight. The length of an existing runway, 9R-27L, just wasn’t long enough anymore at 5300 feet (1615 m). The Broward County Board of County Commissioners created a plan to extend their southern runway to 8000 feet (2438 m) to accommodate the larger commercial aircraft in operation today.

The project isn’t as simple as tearing out the existing runway and building a new one in its place. To create enough area for the longer runway, a new 60 foot (18.3 m) high man-made embankment had to be built. If that wasn’t enough of a challenge, to the west of the new embankment, concrete bridge structures had to be built to support the runway extension and adjacent taxiway as it crossed over U.S. Highway 1 and the Florida East Coast Railroad line.

Archer Western Construction LLC, based in Tampa, Florida, won the bid for the grade work, subbase preparation, and concrete slipforming of the airport’s new runway and taxiway. Due to delays on the project, they had to carry out their portion of the work while the other major contractors finished the embankment and bridge structures.

Their paver for the project was a GOMACO four-track GHP-2800 with Leica Geosystems 3D machine guidance. The GHP-2800’s job-site mobility, along with it being a stringless project, would allow them to pave when and where they needed amongst the crowded project site.

“Archer Western came in and did the topping off, let’s just say, of the project,” Justin Cooper, Project Manager for the company, said. “It was a nice GOMACO project. For our subbase, we used the 9500 placer. On the concrete paving we used a PS-2600 placer/spreader with a GHP-2800 paver setup at 18.75 feet (5.7 m) wide, followed by a T/C-600 texture/cure machine. We ran stringless with a Leica Geosystems setup. Then, for our hand pours, we used the 9500 and RTP-500 placers.”

 

 

Fort Lauderdale-Hollywood International Airport

The new southern runway at the Fort Lauderdale-Hollywood International Airport was built on a 60 foot (18.3 m) high man-made embankment that crosses over an existing highway and railroad line.

 

GHP-2800

The GHP-2800, using a Leica Geosystems 3D guidance system, comes off the evening’s header and paves down ramps off the new 16.5 inch (419 mm) thick section of runway.

 

 

 

Paving work on the new runway began in February last year. As grade work was completed, subbase could be placed. Archer Western used their GOMACO 9500 to place the six inch (152 mm) thick cement-treated base (CTB). Originally, the plan was to pave the new 8000 foot (2438 m) long concrete runway in 2000 foot (610 m) sections. Project phasing wouldn’t allow for that and paving runs were shortened to 1500 feet (457 m) in 10 hour shifts.

The concrete for the project was mixed on site in the company’s portable batch plant. Requirements called for a standard P-501concrete, 650 flex airfield mix. The concrete had fly ash added and used manufactured sand instead of natural sand. Slump averaged 0.75 inches (19 mm). The plant batched 10 cubic yard (7.6 m3) loads and eight to 10 trucks worked to supply the concrete to the paving site.

The end-dump trucks unloaded onto the large conveyor belt mounted on the left side of their GOMACO PS-2600 placer/spreader.

“This was a basket job with dowel baskets every 20 feet (6.1 m). The dowels were 1.5 inches (38 mm) and placed on 18 inch (457 mm) centers,” Cooper explained. “With the slump of the concrete being as low as it was, you get that initial set and the PS-2600 placer gives you a better tolerance for running that GHP-2800 behind it and achieve a smooth finish.”

Their GOMACO four-track GHP-2800 slipformed the new runway in 18.75 foot (5.7 m) wide, 16.5 inch (419 mm) thick paving passes with a standard crown down the middle. At that width and thickness, each lineal foot (305 mm) of new runway lane required nearly one cubic yard (0.8 m3) of concrete.

The paver is equipped with a Leica Geosystems 3D guidance system, eliminating stringline from the site. Since most of Archer Western’s paving is done at night to accommodate the subtropical heat of southern Florida, the 3D system offered a distinct advantage.

“There’s nothing to trip over,” Cooper said. “At night we used to have to make sure we had lighting all the way up and down the project so the guys didn’t run into the stringline. Now, we don’t have to set up the whole lane at once. We can move the light plants along with the paving equipment. That’s nice.

“It’s worked out well for us. We also used our Leica Geosystems setup on the CTB placement, so we went stringless all the way from subgrade up. We had some initial setup with 3D getting things warmed up and getting the system down. We’ve learned to do a dry run at the beginning of each shift. We’ll back the paver up 60 feet (18.3 m) prior to the actual concrete coming into place to make sure the paver is coming in at the right elevation and not making any adjustments when it gets to the start of the paving.”

 

 

PS-2600 placer/spreader, GHP-2800 paver, and T/C-600 texture/cure machine

 

PS-2600 placer/spreader, GHP-2800 paver, and T/C-600 texture/cure machine

 

Archer Western Construction LLC slipformed the new 8000 foot (2438 m) southern runway with their GOMACO PS-2600 placer/spreader, GHP-2800 paver, and T/C-600 texture/cure machine.

 

 

Mother Nature proved challenging as well on the project. Rain showers would hit every night, sometimes twice each night, and the Archer Western crew had to be ready to cover their fresh concrete at a moment’s notice.

“This is a first for me to come pave this far south and when we were in the heat of paving, it would rain just about every day,” Cooper said. “At first we wondered how in the world are we going to pave this with all of the rain? The guys became good meteorologists out in the field at night and we did a lot of covering with plastic.”

Slipforming the runway was divided into eight paving lanes. Smoothness specifications using the two-tenths blanking band and edge slump requirements had to be met on all areas of the new concrete pavement.

“Our quality is very good on the pavement and we took no deductions for PWL (percent within limits) specifications,” Cooper said. “We were allowed a 16 foot (4.9 m) straightedge and had to use a two-tenths blanking band with a profilograph. Seven inches per mile (110 mm/km) was the cutoff for payment and we typically ran in the two inches per mile (32 mm/km) range.

“When we ran our straightedge behind the machine, we had to ensure there was not excessive edge slump as part of our quality checks. That was the biggest challenge because that manufactured sand is a little harder to finish, but the paver handled it and built a good edge.”

A GOMACO T/C-600 texture/cure followed the paver applying a burlap drag finish and a white spray cure. Transverse joints were saw cut into the new runway every 20 feet (6.1 m).

With the project complete, the new runway’s designation changed from 9R-27L to 10R-28L and the Fort Lauderdale-Hollywood International Airport is operating more efficiently with fewer delays.

“We did a lot of concrete work in a small amount of time, basically completing the runway portion of the project in five months,” Cooper explained. “We’ve had a lot of good feedback about the new runway and the tower is very happy to have a second runway operational.”

 

 

 

 

GOMACO World Index

Subscribe to Receive GOMACO World Magazine